Revised 2002 Basin Management Plan Documents
Background and Purpose
The Basin Management Plan (BMP) is the key, principal document that guides all of the major projects and programs pursued by the Agency. The "revised" version of the BMP was adopted by the Agency's Board of Directors in February 2002. The Agency's first BMP was previously adopted in 1994. A redraft of the BMP was prepared in 2000 but was delayed so that more analysis of local water supply options could be evaluated and incorporated into this plan. The Basin Management Plan was then updated in 2014.
During the preparation and review of the revised BMP, the Agency analyzed combinations of 14 different project components and five different management strategies. The final strategy adopted by the Board was called the "Modified BMP 2000 Alternative" and included the following five major projects and programs: 1) Coastal Distribution System pipelines, 2) Recycled Water Project, 3) Harkins Slough recharge Project, 4) 54-inch import water pipeline project (11,900 acre-feet of imported supply) with local aquifer storage and recovery and, 5) a water conservation program.

In addition to providing a plan for the Agency to pursue, the BMP is also a "basin-wide groundwater management plan" meeting the requirements of California's AB 3030 Groundwater Management Act.
2002 Basin Management Plan Documents
The BMP can be downloaded as a complete document or each section of the BMP can be downloaded as a separate PDF file:
- Complete BMP [25,700K]
- Table of Contents [17K]
- Executive Summary [16,192K]
- Section 1: Purpose and Introduction [48K]
- Section 2: State of the Basin [12,042K]
- Section 3: Management Measures- analyzes 4 management options to reduce water use [815K]
- Section 4: New Water Supply Projects-- describes all 14 viable water supply project alternatives of which 4 were recommended and adopted. [1,674K]
- Section 5: BMP Strategies--compares four alternative management strategies (combinations of projects and programs). [1,604K]
- Section 6: BMP Recommendation--describes the recommended (and adopted) management strategy in more detail. [817K]
- Section 7: Implementation Plan--describes how the recommended strategy will be implemented and phased. [557K]
- Section 8: Rate Plan-- describes and analyzes the rate plan to pay for the recommended strategy. [91K]
Environmental Impact Report for Basin Management Plan
The EIR can be downloaded as a complete document or each section of the EIR can be downloaded as a separate PDF file:
- Complete EIR (20,620K)
- Cover (674K)
- Table of Contents (33K)
- Acronyms (22K)
- Summary (154K)
- Chapter 1 – Introduction (46K)
- Chapter 2 – Project Description (4,328K)
- Chapter 3 – Regional Setting (4,851K)
- Chapter 4 – BMP 2000 Alternative – Setting, Impacts and Mitigation Measures (3,157K)
- Chapter 5 – Local-Only Alternative – Setting, Impacts and Mitigation Measures (1,060K)
- Chapter 6 – Other Alternatives (737K)
- Chapter 7 – Growth Inducement Potential (83K)
- Chapter 8 – Impact Overview (70K)
- Chapter 9 – Report Preparers (11K)
- Appendices (6,807K)
Draft Environmental Impact Statement for Basin Management Plan
- Cover Sheets (254K)
- Summary (102K)
- Table of Contents (16K)
- Chapter 1 - Purpose and Need (169K)
- Chapter 2 - Alternatives Including the Proposed Action (1,685K)
- Chapter 3 - Affected Environment (817K)
- Chapter 4 - Environmental Consequences (373K)
- Chapter 5 - Consultation and Coordination (27K)
- Chapter 6 - List of Preparers (14K)
- Chapter 7 - References (40K)
- Chapter 8 - Acronyms, Abbreviations, and Glossary (43K)
- Map Appendix (4,342K)
- Appendix A (91K)
- Appendix B (21K)
- Appendix C (36K)
- Appendix D (230K)
- Appendix E (15K)
- Appendix F (12K)
- Appendix G (34K)
- Appendix H (138K)
Related Information
- Frequently Asked Questions about the Basin Management Plan
- State Department of Water Resources AB 3030 Groundwater Management Act